In short
- Every SR&ED claim rests on three tests: technological uncertainty, systematic investigation and technological advancement.
- An uncertainty is the question the technology could not answer. A hypothesis is one idea you tested to answer it.
- The T661 asks for both in writing: line 242 for the uncertainties, line 244 for the work, line 246 for what you learned.
- A hypothesis that failed still counts. A result of "this does not work" is new knowledge.
Why the words matter
SR&ED (sometimes written SRED) is Canada's tax incentive for research and development. The CRA reviews claims using a small set of terms, and each one has a specific meaning. Using them the way the CRA does makes a claim easier to read, and much easier to defend if it is reviewed.
This page explains each term in a sentence or two. For the full rules on what qualifies, see What work qualifies for SR&ED?.
Technological uncertainty
A technological uncertainty is a question about how to reach a technical goal, or whether it can be reached at all, that a competent professional in the field could not answer from standard practice or published knowledge. You only find the answer by experimenting.
A good uncertainty names the technology, the target and why the usual approach falls short. It is about the technology, never about how the team felt. Business questions, like whether a product will sell, do not count.
- Weak: "We were not sure we could make the drink last longer." It describes the team, and gives no target.
- Strong: "Can a cold pressed juice keep its vitamin C above 80% of the starting level for 45 days without heat treatment? Standard high pressure processing holds it for 21."
A quick check
Ask: could an experienced professional look the answer up, or work it out with known methods? If yes, it is standard practice, not an uncertainty.
Hypothesis
A hypothesis is one idea that might resolve an uncertainty, written down before you test it. It says what you will change, the result you expect and why you expect it. One uncertainty usually has several hypotheses, tested one after another.
A pattern that works
If we change this, then this measure will reach this target, because of this reason.
- Weak: "Try a different pressure setting." There is no expected result and no reason, so it reads as trial and error.
- Strong: "If we add 0.2% of an acerola extract before pressing, vitamin C stays above 80% for 45 days, because the extract slows oxidation in the first week, when most of the loss happens."
A rejected hypothesis is not wasted. It is evidence that the answer was not obvious, which is the point of the uncertainty test. Keep it, with its measured result.
Systematic investigation
A systematic investigation is the planned way you work through an uncertainty. The CRA describes four steps:
- Define the problem (the uncertainty).
- Put forward a hypothesis.
- Plan and run tests or analysis to check it.
- Draw conclusions from the results, and decide what to try next.
Trying things until one works, with no record of what was expected or measured, does not show a systematic investigation, even when the work was hard.
Technological advancement
A technological advancement is the new knowledge the work produced: something about the technology that was not known before, even if the project failed. Learning why an approach cannot work is an advancement. A product that works but taught you nothing new about the technology is not.
Claim and filing terms
- SR&ED
- What it meansScientific Research and Experimental Development. Under the Income Tax Act it covers basic research, applied research and experimental development, plus some support work that directly backs them.
- Standard practice
- What it meansWork a competent professional could do with known methods: routine engineering, testing for quality, ordinary bug fixing. It does not qualify on its own.
- Form T661
- What it meansThe CRA form for an SR&ED claim. Part 2 is the written project description; the other parts cover spending.
- Lines 242, 244 and 246
- What it meansThe three written answers in Part 2 of the T661: line 242 for the technological uncertainties, line 244 for the work done to overcome them, in date order, and line 246 for the advancements achieved or attempted.
- ITC
- What it meansInvestment tax credit: the SR&ED credit itself, worked out on Schedule 31 of the corporate tax return.
- CCPC
- What it meansCanadian-controlled private corporation. A CCPC can earn a 35% credit on its first $6M of eligible spending a year, paid as a refund even when it owes no tax, and 15% above that. Since the 2026 changes, eligible Canadian public corporations can also earn 35% on up to $6M. Most other companies earn 15%.
- Refundable credit
- What it meansA credit paid out as cash when it is more than the tax you owe, so a company with no profit can still receive it.
- Proxy method
- What it meansA simple way to claim overhead: an extra 55% of eligible salaries, with no receipts. The other choice is to claim actual overhead costs.
- Government assistance and contract payments
- What it meansGrants, other government help and payments from customers for the same work. They lower the spending you can claim.
- Filing deadline
- What it meansFor most corporations, 18 months after the end of the tax year the work was done in. A late claim is not accepted.
| Term | What it means |
|---|---|
| SR&ED | Scientific Research and Experimental Development. Under the Income Tax Act it covers basic research, applied research and experimental development, plus some support work that directly backs them. |
| Standard practice | Work a competent professional could do with known methods: routine engineering, testing for quality, ordinary bug fixing. It does not qualify on its own. |
| Form T661 | The CRA form for an SR&ED claim. Part 2 is the written project description; the other parts cover spending. |
| Lines 242, 244 and 246 | The three written answers in Part 2 of the T661: line 242 for the technological uncertainties, line 244 for the work done to overcome them, in date order, and line 246 for the advancements achieved or attempted. |
| ITC | Investment tax credit: the SR&ED credit itself, worked out on Schedule 31 of the corporate tax return. |
| CCPC | Canadian-controlled private corporation. A CCPC can earn a 35% credit on its first $6M of eligible spending a year, paid as a refund even when it owes no tax, and 15% above that. Since the 2026 changes, eligible Canadian public corporations can also earn 35% on up to $6M. Most other companies earn 15%. |
| Refundable credit | A credit paid out as cash when it is more than the tax you owe, so a company with no profit can still receive it. |
| Proxy method | A simple way to claim overhead: an extra 55% of eligible salaries, with no receipts. The other choice is to claim actual overhead costs. |
| Government assistance and contract payments | Grants, other government help and payments from customers for the same work. They lower the spending you can claim. |
| Filing deadline | For most corporations, 18 months after the end of the tax year the work was done in. A late claim is not accepted. |
For how these fit together when you file, see How to file an SR&ED claim. For the money side, see How the SR&ED refund works.
Record keeping terms
- Contemporaneous records
- What it meansRecords made at the time the work happened: tickets, test logs, lab notes, commits, meeting notes. The CRA gives these the most weight.
- Supporting evidence
- What it meansAnything that backs up what the claim says: test results, design notes, prototypes, data and who worked on what.
- Claim preparer
- What it meansThe accountant or SR&ED consultant who prepares the claim. The T661 asks you to name them and how they are paid.
- Pre-claim approval
- What it meansAn optional CRA review, from April 1, 2026, that tells you before you file whether planned work is likely to qualify.
| Term | What it means |
|---|---|
| Contemporaneous records | Records made at the time the work happened: tickets, test logs, lab notes, commits, meeting notes. The CRA gives these the most weight. |
| Supporting evidence | Anything that backs up what the claim says: test results, design notes, prototypes, data and who worked on what. |
| Claim preparer | The accountant or SR&ED consultant who prepares the claim. The T661 asks you to name them and how they are paid. |
| Pre-claim approval | An optional CRA review, from April 1, 2026, that tells you before you file whether planned work is likely to qualify. |
To see how to write records that hold up, see How to write up an SR&ED task.
Examples by industry
The terms are easiest to learn from worked examples. How to write up an SR&ED task has twenty, across software, engineering, manufacturing, food and life sciences. Each one starts from a weak task, then shows the uncertainty, the hypotheses, the tests and the results written to hold up.
Frequently asked questions
What is the difference between an uncertainty and a hypothesis?
The uncertainty is the question: what the technology could not yet do. A hypothesis is one possible answer you can test. One uncertainty usually has several hypotheses, each with its own test and result.
What does standard practice mean for SR&ED?
Work a competent professional in the field could do using known methods, without experimenting to find the answer. It is excluded even when it takes skill and time.
What does contemporaneous mean in SR&ED?
Made at the time. Contemporaneous records were written while the work happened, not reconstructed at claim time. They carry the most weight in a review.
What is an ITC in SR&ED?
An investment tax credit. It is the SR&ED credit itself: a percentage of your eligible spending, calculated on Schedule 31 of the corporate return.
Does a failed experiment count as an advancement?
Yes, when it taught you something new about the technology. Showing why an approach cannot work is an advancement. Keep the hypothesis and the measured result.
Prepare your SR&ED claim with Sredify
Connect the tools your team already uses, see which work may qualify, and build a claim with every hour traced to its source.
Sign in to get startedSources
- CRA: SR&ED eligibility (the steps of a systematic investigation)
- CRA: Guidelines on the eligibility of work for SR&ED tax incentives
- CRA: Guide to Form T661 (T4088)
- Income Tax Act s. 248(1): definition of SR&ED
- Income Tax Regulations s. 2900 (proxy amount)
This guide explains the general rules. It is not tax advice: talk to your accountant or SR&ED preparer about your own claim.